Energy Minister Bill Bennett

Site C dam construction to start next summer

Province to take less revenue from BC Hydro to minimize its debt, says $8 billion project is the cheapest available option to meet demand

The B.C. government has given the go-ahead for BC Hydro to start construction on a third dam on the Peace River, with a delay of six months to try to work out settlements with area aboriginal communities and landowners whose properties will be flooded or cut off.

Energy Minister Bill Bennett said Tuesday an update of the construction costs upheld the $7.9 billion estimate for the Site C dam that was developed in 2010, but the estimate has risen.

Delaying the project six months from its original start date adds inflation and interest costs, and calculating the effect of the provincial sales tax replacing the HST bringing the total to $8.34 billion, and the province is establishing a “project reserve” of $440 million to bring the total estimated cost to $8.77 billion.

The project reserve is in case of unforeseen events such as a rise interest rates during the eight-year construction period.

BC Hydro CEO Jessica McDonald said the six-month delay provides time to work out agreements with Treaty 8 First Nations who have declined settlement offers. The federal-provincial environmental review panel gave the go-ahead for the project in May, but noted its unavoidable impacts on aboriginal hunting, fishing and trapping rights that are assured by the 1899 treaty.

A group of Peace valley landowners has already started legal action against the project, having refused offers from BC Hydro to buy their land. Aboriginal groups in Alberta, downstream of the project, have also started court action against it.

NDP leader John Horgan called the decision “a $9 billion gamble” and repeated his call for a review by the B.C. Utilities Commission to see if the additional power is going to be needed by the time the dam is operating in 2025.

The BCUC will determine BC Hydro rates in the years ahead, and how much they will go up to pay for the most expensive public construction project in B.C. history. The government plans to mitigate BC Hydro rate impact by reducing the dividend the government takes from the power company’s operations each year.

Bennett said a review of alternative clean energy sources, including wind, solar and geothermal power, showed they can’t compete on price because they are intermittent sources that would require backup power.

 

Just Posted

Multi-family housing zoning passed

The way is partly paved for 11 new multi-family strata buildings to go up in Smithers

Two Smithers bowlers go to nationals

Madison Richter and Peyton Pettigrew are heading to Oshawa after winning gold at B.C. provincials.

New Work BC office scheduled to open April 1

Kopar Administration, the new Work BC contractor, still looking to fill positions in Smithers office

Gryphons girls graduate as coach moves on

Bulkley Valley SD54 van der Mark on his time as coach and education administrator.

Bulkley Valley members of The North Matter rally in Houston

Pro-pipeline and resource development group driving convoy Saturday, eyes expansion across the North

Sparks fly as SUV speeds down wrong side of Highway 1 trying to flee RCMP

Captured on video, the vehicle headed westbound against oncoming traffic before crashing

Trudeau in Vancouver to support Tamara Taggart at Liberal nomination event

The former broadcaster is seeking the nomination for the Vancouver Kingsway riding

Trudeau calls May 6 byelection for B.C. riding of Nanaimo-Ladysmith

The riding opened up when Sheila Malcolmson resigned in January

B.C. VIEWS: The hijacking of our education system gathers speed

Children taught to strike and shout fringe far-left demands

Judges on Twitter? Ethical guidance for those on the bench under review

Canadian judges involvement in community life are among issues under review

Calgary captain has 3 points as Flames torch Canucks 3-1

Giordano leads way as Alberta side cracks 100-point plateau

1,300 cruise ship passengers rescued by helicopter amid storm off Norway’s coast

Rescue teams with helicopters and boats were sent to evacuate the cruise ship under extremely difficult circumstances

B.C. university to offer first graduate program on mindfulness in Canada

University of the Fraser Valley says the mostly-online program focuses on self-care and well being

Province announces $18.6 million for B.C. Search and Rescue

The funding, spread over three years, to pay for operations, equipment, and training

Most Read