LNG Kitimat work camp takes shape

Extensive worker camp now being assembled

Born in Ireland but having spent years overseeing liquefied natural gas (LNG) construction projects in Australia, LNG Canada’s just-arrived general manager for its $40 billion facility in Kitimat is firm about his expectations.

“We want this to be the safest project on earth,” Vince Kenny says of construction which has just passed the one year mark leading to a planned finish in 2024.

With just under 1,000 people now working at the 400-hectare site, now is the time to cement that standard, he says.

“By the time we get to 5,000 people, we will have that culture in place,” Kenny said, emphasizing this project will be his seventh. “Unless we’ve got a culture, all the systems, processes and procedures are ineffective.”

Employees begin each shift reviewing the work plan, a procedure called a toolbox discussion.

“We’re here to take care of one another,” says Kenny, translating the IIF acronym that’s the hallmark of LNG Canada — Incident and Injury Free.

Even a brief tour of the works by a group of journalists from across B.C. starts with a video of LNG Canada workers outlining safety and security, the two words being almost interchangeable.

Workers have ID cards to be ‘badged in,’ creating an electronic record of their presence. They’re required to stay within their designated work area.

There are constant security patrols. Vehicles are inspected for any fluid leaks before entry.

There’s specific mention of drug-sniffing dogs too.

READ MORE: Okanagan company wins contract for LNG Canada project in Kitimat

No one gets on the site without basic safety equipment — hardhat, safety glasses, a high visibility vest, work boots and gloves. The driver of the tour bus taking the journalists to the site points out emergency exit windows. He brandishes a small hammer to smash a window if necessary. The bus doesn’t move until each passenger clicks in their seatbelt.

Victor Kenny, LNG Canada general manager

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

Those processing modules being built in Asia are to be 70 metres long, 35 metres wide and 50 metres tall, the approximate height of a 13-storey commercial building.

They’ll be shipped to Kitimat in modular segments and assembled on-site, being transported to their final resting place via an elaborate series of interconnected trailers with hundreds of wheels controlled by a single operator using a remote control.

So sophisticated is the transport system that the operator is able to place the modules within centimetres of where they need to be located.

The sheer height of the modules has meant raising Rio Tinto BC Works’ power lines that cross the site to deliver power to the smelter from Kemano, so that the modules can fit comfortably underneath when being moved.

One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge, which is being built by the ATCO-Bird joint venture, for another joint venture between Fluor Corporation and JGC, the overall general contractor on the project.

There’ll be two living unit sections with a series of common buildings in the middle.

One of the modular accommodation sections is now being assembled with a finishing schedule of next spring to meet a first goal of 1,500 “heads in beds” with 1,000 more beds to be added each quarter thereafter to the final total of 4,500.

Unlike camps of past, each worker will have his or her own bathroom and each room will have its own TV. There will be sound dampening and other acoustic methods so that sleeping quarters will be as quiet as possible. The living areas will be co-ed.

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, an entertainment centre, a licensed lounge, a medical clinic, storage for luggage and housekeeping and maintenance facilities.

There’ll be landscaping around the area and informational material describes the facility as having the “largest core footprint” of its kind in Canada.

“You want your workers to come here and then want to come back,” said LNG Canada spokesperson Susannah Pierce of the atmosphere and amenities of the facility.

More than 4,500 people will be onsite at any one time at the peak of construction, requiring between 7,000 to 7,500 people in all given the shift work nature of the project. Workers will be onsite for 14 days at a time, returning after a seven-day break.

With accommodation facilities now underway, there’s other activity on the waterfront at two terminal sites.

LNG Canada is building Rio Tinto a new wharf in exchange for taking over the aluminum smelting company’s existing wharf. Dredging is now going on as part of that project.

kitimatLNGlng canada

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

Just Posted

No charges to be laid against 22 pipeline protesters arrested on Wet’suwet’en territory

Twenty-two people were arrested in February, but Crown has decided not to pursue charges

Salvation Army celebrates National Doughnut Day with deliveries to front line COVID workers

National Doughnut Day pays tribute to the “Doughnut Lassies” of the First World War

Houston mill to re-open June 8

Ends lengthy shutdown which began in March

Fibre installation for South Hazelton begins

Citywest says it will install cable in the summer and home installations in the fall

Annual bird count thrills organizer

Count took place over 48 hours

‘I’m pissed, I’m outraged’: Federal minister calls out police violence against Indigenous people

Indigenous Minister Marc Miller spoke on recent incidents, including fatal shooting of a B.C. woman

Kelowna Mountie who punched suspect identified, condemned by sister

‘How did he get away with this? How is this justifiable?’

PHOTOS: Anti-racism protesters gather in communities across B.C.

More protests are expected through the weekend

Pair accused of ‘horrific’ assault at Vancouver’s Oppenheimer Park at large

Police say Jason Tapp, 30, and Nicole Edwards, 33, did not show up to meet their bail supervisor this week

Introducing the West Coast Traveller: A voyage of the mind

Top armchair travel content for Alaska, Yukon, BC, Alberta, Washington, Oregon and California!

‘Great Regional Air Hug’ being organized by the Vanderhoof International Airshow Society

A multi-aircraft flyover over the region is being planned for August 15.

Plan in place for BC Ferries to start increasing service levels

Ferry corporation reaches temporary service level agreement with province

B.C. starts to see employment return under COVID-19 rules

Jobless rate for young people still over 20% in May

Most Read