Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepencies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Smithers man leaves $1 million to children’s hospital

Jim Bolster wanted to help out children with health problems like his own

QUIZ: How much do you know about British Columbia?

On this B.C. Day long weekend, put your knowledge of our province to the test

New ownership resurrects BV Taxi

The new owners expect to be taking fares by mid-August

Tahltan Nation closes hunting and recreational activity access points

The remote and vulnerable territory has limited medical capacity

Kinsmen plan to host scaled-down version of Telkwa BBQ

Club hoping to serve traditional Beef on a Bun and keep status of longest running event in B.C.

VIDEO: Otter pups learn to swim at B.C. wildlife rescue facility

Watch Critter Care’s Nathan Wagstaffe help seven young otters go for their first dip

Michael Buble among 13 British Columbians to receive Order of B.C.

Ceremony will be delayed to 2021 due to COVID-19

U.S. border communities feel loss of Canadian tourists, shoppers and friends

Restrictions on non-essential travel across the Canada-U.S. border have been in place since March 2`

Rollout of COVID-19 Alert app faces criticism over accessibility

App requires users to have Apple or Android phones made in the last five years, and a relatively new operating system

Alleged impaired driver sparks small wildfire near Lytton after crash: B.C. RCMP

Good Samaritans prevented the blaze from getting out of control

B.C. First Nation adopts ‘digital twinning’ software to better manage territory

Software allows users to visualize what a mountain might look like if the trees on its slopes were logged

All inquiry recommendations implemented after fatal Port Hardy RCMP shooting: Ministry

The Independent Investigations Office of B.C. cleared the RCMP officers involved of wrongdoing

Most Read