Coastal GasLink has successfully completed its winter construction program, in time for the spring thaw.

Coastal GasLink wraps up winter construction

This week, Coastal GasLink concluded its winter construction program in time for the spring thaw. With the change in season, the project has completed its planned reduction in workforce numbers to approximately 400, down from 1,200 in February.

According to Dan Bierd, Coastal GasLink’s vice-president of pipeline implementation, the scheduled ramp-down concludes a successful winter construction season.

“Over the past several months, we have accomplished many important milestones,” said Bierd, “including the clearing of more than 65 per cent of the 670-kilometre right-of-way.”

“And most importantly,” added Bierd, “we achieved all of this with safety as our top priority, and with the hundreds of Indigenous and local residents as part of our workforce.

“We’re proud of our safety record this winter that saw over four million person-hours of work undertaken on hazardous clearing activities that were completed without serious incidents or injury.”

The start of spring means that melting snow and thawing conditions make the ground either too soft or too muddy for trucks, machinery and people to work. That, coupled with the sensitive migration stages for birds, fisheries and other wildlife species make this a good time for crews to take a break.

“We’re going to focus our smaller team of local workers and contractors on critical activities such as environmental monitoring, sediment and erosion control, and site-specific activities including maintenance,” noted Bierd.

The smaller and more local workforce has also allowed Coastal GasLink to strengthen the focus on the health and safety of the workforce and communities and do its part to help slow down the spread of COVID-19.

“Safety is our number one value, and our first concern is for all the employees, families and communities who may be affected by this situation,” said Bierd. “We send our sincerest well-wishes to everyone and recognize the tremendous efforts of first responders and health professionals worldwide.”

Coastal GasLink is taking proactive steps to help slow down the spread of the virus. Plans are in place and measures being taken help protect the health of the critical teams at work and all non-essential staff are working remotely and air travel restricted.

In addition to social distancing, CGL is engaged with health and medical experts, including Northern Health, ensuring workers have continued medical coverage, working primarily with local workers for essential activities and minimizing the number of residents at workforce accommodation sites, which will continue to fall as work is further reduced along the route.

“We recognize even more so now that we have to work together and look out for one another. We will offer our assistance in support of local efforts to keep residents safe,” said Bierd.

Coastal GasLink has been working closely with provincial health authorities and have been taking the advice of the Provincial Health Officer as they continue essential project work and will continue to seek their advice prior to resuming construction.

“We will overcome this challenge, and we look forward to continuing to work together when project construction resumes to deliver significant economic benefits to British Columbian families for the long-term,” he added.

Learn more and stay connected at www.CoastalGasLink.com

energy sector

 

Coastal GasLink’s reduced workforce comprising primarily local workers is focused on critical activities such as environmental monitoring and site security.

Just Posted

No charges to be laid against 22 pipeline protesters arrested on Wet’suwet’en territory

Twenty-two people were arrested in February, but Crown has decided not to pursue charges

Salvation Army celebrates National Doughnut Day with deliveries to front line COVID workers

National Doughnut Day pays tribute to the “Doughnut Lassies” of the First World War

Houston mill to re-open June 8

Ends lengthy shutdown which began in March

Fibre installation for South Hazelton begins

Citywest says it will install cable in the summer and home installations in the fall

Annual bird count thrills organizer

Count took place over 48 hours

‘I’m pissed, I’m outraged’: Federal minister calls out police violence against Indigenous people

Indigenous Minister Marc Miller spoke on recent incidents, including fatal shooting of a B.C. woman

Kelowna Mountie who punched suspect identified, condemned by sister

‘How did he get away with this? How is this justifiable?’

PHOTOS: Anti-racism protesters gather in communities across B.C.

More protests are expected through the weekend

Pair accused of ‘horrific’ assault at Vancouver’s Oppenheimer Park at large

Police say Jason Tapp, 30, and Nicole Edwards, 33, did not show up to meet their bail supervisor this week

‘Great Regional Air Hug’ being organized by the Vanderhoof International Airshow Society

A multi-aircraft flyover over the region is being planned for August 15.

Plan in place for BC Ferries to start increasing service levels

Ferry corporation reaches temporary service level agreement with province

B.C. starts to see employment return under COVID-19 rules

Jobless rate for young people still over 20% in May

Williams Lake RCMP capture fugitive walking along Highway 97 in city limits

Witness said they could hear police yelling for suspect to ‘get down’

Most Read