Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Lake Babine Nation councillor resigns before being sworn in

Paul Joseph steps down before being sworn in

Kevin Kriese becomes chair of the Forest Practices Board

Smithers’ Kriese’s three-year appointment beings August 7.

Moricetown Mud Bog stuck in a rut for 2018

A busy personal life for organizers means there will be no Moricetown Mud Bog in Witset this year.

Smithers ‘way ahead’ on preparing for pot

Public consultation around town on pot use, dispensing and licensing this summer.

Update on contaminated mine sites program

The report details work done over the past two years to remediate contaminated sites.

BC Games: Day 1 comes to an end

Medals have already been handed out following one day of competition in the 2018 BC Summer Games

BC Wildfire update on Okanagan blazes

Watch the media briefing on the current fire situation in the Okanagan.

UPDATED: Evacuation alert issued due to Dog Creek Trail Wildfire

UPDATED: The Dog Creek wildfire has grown substantially over the past two… Continue reading

RCMP help to save goats from wildfire

The fast-approaching wildfire, sparked Thursday, forced the evacuation of five homes

VIDEO: Near drowning captured on popular B.C. river

Search and Rescue manager says the popular pastime of floating in the summer is inherently dangerous

Crosswalk vandalism leaves black mark for Cowichan as B.C. Games begin

Rainbow crosswalk defaced just days after being painted

Photo gallery: BC Games Day 1

A brief look at action from the 2018 BC Summer Games in the Cowichan Valley

UPDATED: Anti-pipeline campers digging in as eviction deadline expires

The City of Burnaby had ordered the Kinder Morgan pipeline protesters out for violating bylaws

Trump was taped talking of paying Playboy model: AP source

Source says former personal lawyer Michael Cohen secretly recorded discussion prior to 2016 election

Most Read